Highly explosive material requiring the highest level of service delivery performance for treatment, cleaning, transport and final disposal.
For this complex project, GSD developed a detailed plan in collaboration with a Western Australian tier 1 mining company and delivered full execution of services covering the following process steps:
2.1 million Tonnes of liquids transported
We transported 2.1 million Tonnes of liquids from various mine sites to Karratha for treatment and processing.
37 triple road train movements
From multiple mine sites across the Pilbara to Karratha return.
42,920km travelled incident free
This is the equivalent of 3 laps around Australia.
Project was successfully carried out over 12 weeks.
Safely executed nil environmental incidents.
300 hours of Confined space tank entries across project.